Mehrshahr urban land development
Location: Karaj – Mehrshahr
Client: Reyhaneh charity institute
Plan and construction services: Tash consulting engineers
Project area: 93430m2
Commencement and completion: 2014 – 2016



Table implementation – March 2015

Fill – May 2015

kanivo installation – May 2015

Excavation – June 2015

Borehole – June 2015

Residential blocks leveling – July 2015

Road bed leveling 12-1 – August 2015

bedding of road 1-12 – September 2015

Edging of road 1-12 – September 2015

Roads tables joining – November 2015

Implant of poplar – November 2015

Implementation of roads tables – November 2015

Pedestrian bedding – December 2015

Roads sub base leveling – December 2015

Implementation of roads sub base – December 2015

Bitumen distribution of road 1-10 – May 2016

Implementation of road base 1-12 – May 2016