Mehrshahr urban land development
Location: Karaj – Mehrshahr
Client: Reyhaneh charity institute
Plan and construction services: Tash consulting engineers
Project area: 93430m2
Commencement and completion: 2014 – 2016
Table implementation – March 2015
Fill – May 2015
kanivo installation – May 2015
Excavation – June 2015
Borehole – June 2015
Residential blocks leveling – July 2015
Road bed leveling 12-1 – August 2015
bedding of road 1-12 – September 2015
Edging of road 1-12 – September 2015
Roads tables joining – November 2015
Implant of poplar – November 2015
Implementation of roads tables – November 2015
Pedestrian bedding – December 2015
Roads sub base leveling – December 2015
Implementation of roads sub base – December 2015
Bitumen distribution of road 1-10 – May 2016
Implementation of road base 1-12 – May 2016