The Azadi residential – commercial complex have 6 blocks- A1، A2، B، C1، C2 and D.
Block A1-A2: The floor and body insulation up to the 3 meters height has been completed, and the foundation reinforcement is being carried out.
Block B: Insulation has been completed and the reinforcement of the entire foundation has been done. The first stage of concreting has been done.
Block C1 – C2: Concreting and foundation operation has been completed.
Block D: Part 1 and 2 of steel structures from level -5 to ground floor has been installed. Infrastructure, installation of body insulation and construction of stable retaining wall on -5th floor have been completed.
Insulation on the north side of level -4 and execution of steel deck roof on levels -4 and -5 are completed. The first stage of reinforcement and concreting of the level -5 roof has been completed.